10 Helensburgh, Cardross and Dumbarton Cyclepath Update PDF 220 KB
Report by Executive Director with Responsibility for Development and Economic Growth
:
Additional documents:
Minutes:
Consideration was given to a report updating
Members on the progress made since the Helensburgh
and Lomond Area Committee on 13 December 2022, in relation to the delivery of a
dedicated, high quality walking and cycle route linking Helensburgh,
Cardross and Dumbarton.
Decision
The Helensburgh
and Lomond Area Committee:-
1. noted the agreement of five change requests from WSP
at an additional cost of £28,538.97, taking the total cost of WSPs work to
£253,427.96. This additional cost is covered by externally secured funding;
2. welcomed the progress made by WSP towards completing
their work package by 31 March 2023;
3. noted that some elements of work will require to be
completed separately during summer 2023 to finalise the full package required
for construction; and
4. noted the current tender exercise for a design
consultant to commence work on the section of route linking Morrisons
Supermarket to Helensburgh Town Centre/Waterfront.
(Reference: Report by
Executive Director with responsibility for Development and Economic Growth,
dated 13 February 2023, submitted)
: